Hello Guys,

In AFS, it's possible to define a RLT at sku group for in-house
production, this is used during ATP check. In release 6.4, an
GREAAATTTTT enhancement was done in PP, which is the support of
production version at sku group. Let's say you spend 1 day to produce
a finished goods for size XXS, and 1,5 for size XXL (maybe more true
for bags or underwear). XXL is longer to produce because you have more
components and more operations, therefore the production time also
depends on the sku group, I would have expect a field "production
time" at sku group too, currently there's only one field at material
level, which is not consistent based on all feature that exist in AFS.

Mehdi