Hello All,

I have question regarding availability check (Checking group ) – MRP3 view ( MARC-MTVFP )

What’s a fallouts or issues if you change checking group from 02 (Consider RLT )to 01 ( NO RLT) ?

Current Customer process is Fashion material – will consider normal stock, IBD, purchase order for atp calculations. So material Group is 02. After season is closed Fashion material is converted to Replenishment material ( Replenishment season is attached ).  

Currently we are thinking of changing checking group from 02(Consider RLT) to 01(No RLT) when material is changed to replenishment material.

Wanted wants to know drawbacks if we change checking group in lifecycle of material.

Thanks,
Vasant

2 comments:

AFS-User-Network said...

ATP doesn’t promise anything if sufficient stock is not available with No RLT leading to rejections in Sales Order. Customer Orders are lost in this case.

- Mahesh

AFS-User-Network said...

Thanks Mahesh. Its Rush order this is fine.

- Vasant