Hello,

In AFS, PIR are reduced after posting sales order goods issue. Like
most of SAP feature, PIR are plant dependent. Let's say you have two
plants (one DC and one production plant), PIR are created in the DC
and both plants have a shipping area. Then depending on the customer
ship to country, it could be interesting to ship the goods from the
production plant because you have there some available quantity. In
such a case, ATP/ARUN substitution could be used but PIR could be
never reduced due to a PGI that happens in the "wrong" plant (not the
DC).

Mehdi